Entries interpreted as days not hours

D

dan.ross

Project Server 2007 PWA question concerning entries being interpreted
as days and not hours unless "h" entered after number entered. I have
set task updating options at the server level to be Tracking Method
"hours worked per period" and Reporting Display to be "Resources
should report hours worked per day". I have set the "timephase view"
on the My task page in order to see the daily time entry view. When I
enter time on this view the entry is interpreted as days and not hours
unless I put an "h" after the entry. The options on the project side
have been set to work is entered in "hours". If I don't set the
"timephase view" option in my tasks and click the progress cell it
brings up a daily entry screen in which my entries are intrepreted as
hours. Am I missing some setting in order to have the "timephase
view" entries be interpreted as hours or is this the way it works?
 
D

Dale Howard [MVP]

Dan --

Try the following:

1. Log into PWA with administrator permissions.
2. Navigate to the My Tasks page.
3. Click the Site Actions pick list and choose the Edit Page option.
4. Click the Edit menu in the My Tasks web part and choose Modify Shared
Web Part.
5. In the sidepane on the right, scroll down and then expand the Project
Web Access section.
6. In the Project Web Access section, set the Work Format value to Hours.
7. Click the OK button.
8. Click the Exit Edit Mode button in the upper right corner of the page.

Do the above steps resolve your problem? Let us know.
 
D

dan.ross

Dan --

Try the following:

1.  Log into PWA with administrator permissions.
2.  Navigate to the My Tasks page.
3.  Click the Site Actions pick list and choose the Edit Page option.
4.  Click the Edit menu in the My Tasks web part and choose Modify Shared
Web Part.
5.  In the sidepane on the right, scroll down and then expand the Project
Web Access section.
6.  In the Project Web Access section, set the Work Format value to Hours.
7.  Click the OK button.
8.  Click the Exit Edit Mode button in the upper right corner of the page.

Do the above steps resolve your problem?  Let us know.








- Show quoted text -

Dale,

Hoo Rah!....thank you very much...your steps worked...man I would
never figured out to do the steps you provided...you are Da Man!

Regards,

Dan
 
D

Dale Howard [MVP]

Dan --

You are more than welcome for the help, my friend! :)




Dan --

Try the following:

1. Log into PWA with administrator permissions.
2. Navigate to the My Tasks page.
3. Click the Site Actions pick list and choose the Edit Page option.
4. Click the Edit menu in the My Tasks web part and choose Modify Shared
Web Part.
5. In the sidepane on the right, scroll down and then expand the Project
Web Access section.
6. In the Project Web Access section, set the Work Format value to Hours.
7. Click the OK button.
8. Click the Exit Edit Mode button in the upper right corner of the page.

Do the above steps resolve your problem? Let us know.








- Show quoted text -

Dale,

Hoo Rah!....thank you very much...your steps worked...man I would
never figured out to do the steps you provided...you are Da Man!

Regards,

Dan
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top