Project Server 2007 PWA question concerning entries being interpreted
as days and not hours unless "h" entered after number entered. I have
set task updating options at the server level to be Tracking Method
"hours worked per period" and Reporting Display to be "Resources
should report hours worked per day". I have set the "timephase view"
on the My task page in order to see the daily time entry view. When I
enter time on this view the entry is interpreted as days and not hours
unless I put an "h" after the entry. The options on the project side
have been set to work is entered in "hours". If I don't set the
"timephase view" option in my tasks and click the progress cell it
brings up a daily entry screen in which my entries are intrepreted as
hours. Am I missing some setting in order to have the "timephase
view" entries be interpreted as hours or is this the way it works?
as days and not hours unless "h" entered after number entered. I have
set task updating options at the server level to be Tracking Method
"hours worked per period" and Reporting Display to be "Resources
should report hours worked per day". I have set the "timephase view"
on the My task page in order to see the daily time entry view. When I
enter time on this view the entry is interpreted as days and not hours
unless I put an "h" after the entry. The options on the project side
have been set to work is entered in "hours". If I don't set the
"timephase view" option in my tasks and click the progress cell it
brings up a daily entry screen in which my entries are intrepreted as
hours. Am I missing some setting in order to have the "timephase
view" entries be interpreted as hours or is this the way it works?