[EPM 2003] Resources availability line is going to zero

P

Pawel

I'm using MS Project Server 2003. If mark some of resources and I
click in PWA 'view resource availability', availability line is flat.

This problem I could see only:
- for 'assignment work by project' (assignment work by resouces looks
fine)
- if I change units for weeks (for day period it alsow looks fine)
- for a few resouces (If I mark one, two or three resouces, problem
doesn't occure)

I've tried regenerate OLAP cube for different period, but it dosen't
solve my problem

Best regards,
Pawel
 
C

Christina

I know that the preference is for people to avoid "me too" posts.

But I am experiencing this same issue today. MSP 2003, PS2003

Looking at resource availability for a couple of resources and receive the
following message:

"Warning: Availability data has not been published for one or more resources
in the selected date range."

For the 2 people impacted, the Resource Availability view is reflecting
their assignments properly, but from November 15th all the way back to when
we installed the server (2005), their availability is showing as zero.
Everything from 11/16 forward is showing the correct availability.
Incidentally, I updated their Resource calendar today to reflect that they
were out of the office today(12/18). Looking at some other resources, the RA
view is fine.

Thoughts?
 
C

Christina

Well, oddly enough, we checked again FRiday morning and the Availability line
for the 2 impacted resources is now reflecting their past availability. I'm
wondering if something hung up when I changed their resource calendar and
didn't fix itself until the OLAP cube rebuilt itself.

Pawel- i'd be interested to hear if you are still experiencing this issue.
 
I

Irish Gues

I have a similar problem going on that I don't know how to fix and I don't
know why it's happening. We restrict resources availability through the
individual's resource information box in the enterprise resources pool. For
example, I am available 50% of the time for project work. When I go into PWA
and go to the resources section and view resource availability with the red
line for availability, the line is typically at 20 hours, which is where it
should be, but once in a while, it drops to 4 hours or 10 hours or some other
number. It seems to be completely random. I am getting ready to give a
presentation to managment on this and I need to get it fixed!! Any ideas?
 
J

Jonathan Sofer [MVP]

Are there holidays set on the standard calendar that could be lowing your
availability on certain weeks?

Jonathan
 
I

Irish Gues

No, not at the time frame I'm looking at...

Jonathan Sofer said:
Are there holidays set on the standard calendar that could be lowing your
availability on certain weeks?

Jonathan
 