EPM 2007 assignment data by day from PSI

I

Idvr

Hi,
I need to get an assignment data (work,actual work, overtime work...) on a
per day basiss. Is there a way to get it using the PSI or I need to create my
own extension to it?

thanks
 
I

Idvr

In second thought:
I can't query the DB because I don't won't the users (the application will
be installed on users desktop) to have to enter a connection string. Using
the PSI I only need the server name.
 
R

Rod Gill

If you're writing a shrink wrapped application then probably PSI is the way
to go, but internally, just get IT to push out a Registry setting with the
connection string when they install your application, or have users browse
to a .txt file on the server with the connection string.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
I

Idvr

OK, so back to the original question: Is there a PSI method to get assignment
data by day or I need to create an extension?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top