J
Jeff1er
Hi all,
One of my customers asked me a question I'm not able to answer, thus
I'm turning towards you:
You know that it is quite simple to set up the max unit at task or
project level by defining, when editing the resource its maximum
capability (e.g.: 50% for an half time working resource).
To view the overall capacity, we can go in the resource center and
checking availability.
But how to set up the maximum capacity of a resource, for instance
someone who's working half time in a project team?
I've been thinking of defining the resource calendar, and providing
here a reduced time slot (let's say 8:00-12:00), but it is reducing
the scope to a time schedule.
Considering the data model, I know we can only tie a resource
capability with a single project, and I'm wondering if there is
another way to do site ?
Any idea ?
One of my customers asked me a question I'm not able to answer, thus
I'm turning towards you:
You know that it is quite simple to set up the max unit at task or
project level by defining, when editing the resource its maximum
capability (e.g.: 50% for an half time working resource).
To view the overall capacity, we can go in the resource center and
checking availability.
But how to set up the maximum capacity of a resource, for instance
someone who's working half time in a project team?
I've been thinking of defining the resource calendar, and providing
here a reduced time slot (let's say 8:00-12:00), but it is reducing
the scope to a time schedule.
Considering the data model, I know we can only tie a resource
capability with a single project, and I'm wondering if there is
another way to do site ?
Any idea ?