J
jlanpher
We have used EPM 2003 since mid-2006 with major frustration. We have
300+ active projects at any moment, with durations from a week to two
years. We use an Infopath based Intake form to input original data
into EPM for display in PWA. We use MSProject to build teams/assign
resources (everyone on team is assigned to the single task known as
'time reporting'), to end a project, and to try to correct data when
MSP's logic changes dates or issues error messages. How do we set up
to be compatible with our needs: Each project has only 1 task, which
is 'time reporting', with 1 to 10 team members. Team members may
participate in any number of projects. We do not pay attention to
members workloads or number of projects or allocate or schedule their
time. Members need to be able to enter as many or as few hours as
they actually put in on each project without the system doing
calculations and issuing error messages or changing dates. We simply
want to assign members to a project with a Start and Finish date and
record their hours. We do not want EPM/MSP to calculate Remaining
Work, change Finish dates, etc. It would be OK for EPM/MSP to not
accept members Task hours before or after Start or Finish date until
Manager changes the date. We would love to have EPM/MSP automatically
approve members hours as submitted.
300+ active projects at any moment, with durations from a week to two
years. We use an Infopath based Intake form to input original data
into EPM for display in PWA. We use MSProject to build teams/assign
resources (everyone on team is assigned to the single task known as
'time reporting'), to end a project, and to try to correct data when
MSP's logic changes dates or issues error messages. How do we set up
to be compatible with our needs: Each project has only 1 task, which
is 'time reporting', with 1 to 10 team members. Team members may
participate in any number of projects. We do not pay attention to
members workloads or number of projects or allocate or schedule their
time. Members need to be able to enter as many or as few hours as
they actually put in on each project without the system doing
calculations and issuing error messages or changing dates. We simply
want to assign members to a project with a Start and Finish date and
record their hours. We do not want EPM/MSP to calculate Remaining
Work, change Finish dates, etc. It would be OK for EPM/MSP to not
accept members Task hours before or after Start or Finish date until
Manager changes the date. We would love to have EPM/MSP automatically
approve members hours as submitted.