I am using Project Server 2007
I have an enterprise flag field on Task lelve, with rollup to summary tasks
(AND).
I have added this field on the My Tasks view so my resources can change this.
Problem is, when they change from No to Yes and this is approved by the
PM... it has changed in the plan on assignment level, NOT on task level.
How can I let my resources change the flag field on task level from the My
Tasks view?
Or how can I rollup the flag field from assignment level to task level
(using OR, so different from rollup to summary tasks)?
Thank you!
I have an enterprise flag field on Task lelve, with rollup to summary tasks
(AND).
I have added this field on the My Tasks view so my resources can change this.
Problem is, when they change from No to Yes and this is approved by the
PM... it has changed in the plan on assignment level, NOT on task level.
How can I let my resources change the flag field on task level from the My
Tasks view?
Or how can I rollup the flag field from assignment level to task level
(using OR, so different from rollup to summary tasks)?