We are using EPM2007 with SP1.
Is there a way to differentiate between the actual work entered by resources
from PWA and the actual work entered by PM through the MS Project, by making
the tasks as 100% complete?
I am looking for the difference into the Reporting Database tables.
Regards,
Viren Saini
We are using EPM2007 with SP1.
Is there a way to differentiate between the actual work entered by resources
from PWA and the actual work entered by PM through the MS Project, by making
the tasks as 100% complete?
I am looking for the difference into the Reporting Database tables.