The SDK details the schema for both cubes with along with an explanation of
their purpose.
--
Please rate this post if it has helped
http://theprojectserverguru.spaces.live.com
- Show quoted text -
All
I have been using PS2007 timesheets and DA views for a long time and
in a number of postings have flagged deficiencies (bugs) in Timesheet
Data Analysis views.
When a timesheet is created the default is to populate it with tasks
scheduled for that week. You can add time to the timesheet in the
following way:
• on a daily basis for pre-populated tasks.
• for pre-populated admin tasks
• You can use insert lines function to add unplanned tasks, summary
tasks, project (top level)
• You can add unverified tasks – an activity not associated with any
project or admin item
The Timesheet cube includes all this data
The EPM Timesheet cube only includes project task level data, i.e. it
excludes admin time, unverified time and summary level task time.
The MSP_Project_Timesheet cube is based on the EPM Timesheet cube and
adds the configured project, resource and task attributes as
dimensions, as well as additional data (costs, baselines etc).
Unfortunately it’s useless as the additional dimensions, though
visible have no numeric data associated with them. See example below.
Note also that all the timesheet excludes tasks which have not had
time booked to them. Comparing the total of the planned work column
with total of Actual Work Billable is therefore of very limited value.
You can see examples here:
http://sleekstone.spaces.live.com/blog/cns!ED36ABFDCD099E3B!149.entry
regards
Mike