Hi.
I have customized a date field with the following formula : IIF
([Name]="Some task name";[Start];"NA")
Calculation for task and group summary rows is set to : Rollup - Maximum.
My aim is to move a certain tasks start date to project field in order to
show it in
Project center.
This produces an ERROR in the custom date field. Any ideas ?
PS Where are the formulas documented - syntax, examples...?
Sorry, if you have encounterd this message elsewhere - I happened to post
it in the archives...
Thank You,
Erkki
I have customized a date field with the following formula : IIF
([Name]="Some task name";[Start];"NA")
Calculation for task and group summary rows is set to : Rollup - Maximum.
My aim is to move a certain tasks start date to project field in order to
show it in
Project center.
This produces an ERROR in the custom date field. Any ideas ?
PS Where are the formulas documented - syntax, examples...?
Sorry, if you have encounterd this message elsewhere - I happened to post
it in the archives...
Thank You,
Erkki