In the task list below, the first row is the project summary task and the
other 3 are summary tasks.
PROJECT SUMMARY TASK - Baseline Work = 701.63 hrs
Iterative/Managerial Tasks - Baseline Work = 360
Project Requirements - Baseline Work = 312.5
Project Closing - Baseline Work = 31
The sum of the baseline work in the bottom three rows is 703.5.
But my project summary task is showing 701.63!!??
Can any one please help me identify solve this error.
Thank you.