#ERROR message for custom field function - Bizarre!

S

shasta1987

I hope someone can help me understand this bizarre problem with a project
plan that I've been using and evolving for the past 1 1/2 years to track a
number of projects on a very high level (Project Portfolio Reporting):

All of a sudden my custom field functions no longer work - even a simple
Today = Now() function. It results in "#ERROR" being displayed. I checked
to make sure that I did not remove any necessary custom fields, tables, etc.
that are used by other calculations. (All looks good) I confirmed that I
have the auto-calculate value set under Tools -> Opotions-> Calculation mode.
I pushed the F9 key just in case as well. If I create a band new project and
I test the "Now()" function in a custom field it works great.

THEN I stumbled onto a fix by adding a bogus new task to my existing file
and all of a sudden everything recalculated and the function returned the
proper value??? Can anyone tell me what is going on?? It is as if MS
Project decided to do a 'recalculate' with this new task I added and then all
is good.

Please help me understand what is going on!
Thank you SO much!
 