#ERROR Message in Calculated Field

T

Thad McLemore

I have a Enterprise Project Cost field whereby I calculate Actual Cost +
Remaining Cost. The field calculates correctly for all the projects except
one. It gives an #ERROR message under the Project Information, Custom Field
Name settings. I've checked the plan and the summaries (line "0" on the
project plan) report the correct values, it just doesn't calculate them
correctly on the Enterprise Project Cost Formula for this project. How do I
begin troubleshooting?

Any help would be appreciated.

Thanks.
 
D

Dale Howard [MVP]

Thad --

Did you try pressing the F9 function key after you open this project? Let
us know.
 
T

Thad McLemore

It's actually now calculating in the Project Information field, don't know
why - nothing has changed. However, it's still showing 0.00 in the web
version in my view.
 
D

Dale Howard [MVP]

Thad --

Now that it's calculating, have you published the project? Let us know.
 