T
Thad McLemore
I have a Enterprise Project Cost field whereby I calculate Actual Cost +
Remaining Cost. The field calculates correctly for all the projects except
one. It gives an #ERROR message under the Project Information, Custom Field
Name settings. I've checked the plan and the summaries (line "0" on the
project plan) report the correct values, it just doesn't calculate them
correctly on the Enterprise Project Cost Formula for this project. How do I
begin troubleshooting?
Any help would be appreciated.
Thanks.
Remaining Cost. The field calculates correctly for all the projects except
one. It gives an #ERROR message under the Project Information, Custom Field
Name settings. I've checked the plan and the summaries (line "0" on the
project plan) report the correct values, it just doesn't calculate them
correctly on the Enterprise Project Cost Formula for this project. How do I
begin troubleshooting?
Any help would be appreciated.
Thanks.