M
mmckeen
Hi, I have master schedule that was originally created in Project 2003 then
updated to 2007. I've inserted another Project plan that was done in Project
2007 into my master. Each time I go to make a change (such as adding a line
item) into the inserted project, I get an error that says "There is a
problem w/ the entry. The accrual choice is not valid..." I've looked at
the resource sheet, and reset the resources used in this inserted project,
but still get the error. Any ideas? The Project files (from what I can
tell) are still OK, but it is annoying to see this message. The message also
appears when I save the the master schedule and click to save all the other
inerted Projects. Thanks!
updated to 2007. I've inserted another Project plan that was done in Project
2007 into my master. Each time I go to make a change (such as adding a line
item) into the inserted project, I get an error that says "There is a
problem w/ the entry. The accrual choice is not valid..." I've looked at
the resource sheet, and reset the resources used in this inserted project,
but still get the error. Any ideas? The Project files (from what I can
tell) are still OK, but it is annoying to see this message. The message also
appears when I save the the master schedule and click to save all the other
inerted Projects. Thanks!