Error on save (timesheet)

M

Matteo

Dear all,
only a user is receiving this message for only a timesheet when he saves it
(only saves).

While communicating with the Project Server an error occured. Check
connectivity with your administrator to determine if further action is
necessary

...it happens when the user add a line (task not scheduled for this week) if
he add hours only to scheduled task all is working fine, adding hours to the
added lines generate the error written below and send a 26000 error to the
mail of the user.

I tried as in other cases to delete the timesheet and recreate it but it's
not the case.

Matteo
 
Y

Y. Lee

Hi Matteo,

We have the same problem with our Projet Server 2007. As soon someone adds a
task not scheduled for this week, she gets this error message.

Does anyone has a solution for this?

Thank you in advance,
Y. Lee
 
M

Mike Mahoney

Hi Matteo,

We have the same problem with our Projet Server 2007. As soon someone adds a
task not scheduled for this week, she gets this error message.

Does anyone has a solution for this?

Thank you in advance,
Y. Lee









- Show quoted text -

Y.Lee

You can make the error go away by changing the timesheet setting to
allow future timesheets.

regards

Mike
 
D

diyah

dear all, i have the same problem in project server 2007

i think that user can add line for task (which task not scheduled for this
week)..
how bout wiht this statement : "You can make the error go away by changing
the timesheet setting to allow future timesheets "?

How to change the setting? I have change the timesheet setting in Server
Settings > Timesheet settings and default > Timesheet Policies > fill check
box : Allow future time reporting. Is it right for the settings?

But the error is still happened.

thanks for your help :)
 
M

Mike Mahoney

dear all, i have the same problem in project server 2007

i think that user can add line for task (which task not scheduled for this
week)..
how bout wiht this statement : "You can make the error go away by changing
the timesheet setting to allow future timesheets "?

How to change the setting? I have change the timesheet setting in Server
Settings > Timesheet settings and default > Timesheet Policies > fill check
box : Allow future time reporting. Is it right for the settings?

But the error is still happened.

thanks for your help :)







- Show quoted text -

Diyah

What is the exact error message in the error log?

Mike
 
D

diyah

the error message when user save timesheet is : “While communicating with the
Project Server an error occured. Check connectivity with your administrator
to determine if further action is necessary “
 
M

Mike Mahoney

the error message when user save timesheet is : "While communicating with the
Project Server an error occured. Check connectivity with your administrator
to determine if further action is necessary "






- Show quoted text -

Hi diiyah
Some questions:

Is this error message which appears at the bottom of the timesheet in
red?
If so what is the error message appearing in the Queue service?

After this message appears if you click save does it go away?

If you the change the timesheet settings (allow future time), and
return to the timesheet does problem persist?

Is this happening for all users or a single user?
Does it happen only in the current week or does also happen in prior
week?

regards

Mike
 