establish a predecessor on a split task

M

meesh1224

I have tasks in a project that needed to be split to accommodate tasks that
took higher priority. Is it possible to set a predecessor on the second half
of the split task so if the higher priority task completes early the split
task is moved back as in a finish to start relationship? Or does it make more
sense to end the incomplete task earlier and add a new task for the remainder
of the incomplete task and have that dependent on the higher priority task?

Thanks,
Michelle
 
G

Gérard Ducouret

Hello Meesh,
Your second hypothesis is the good one !

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top