I have tasks in a project that needed to be split to accommodate tasks that
took higher priority. Is it possible to set a predecessor on the second half
of the split task so if the higher priority task completes early the split
task is moved back as in a finish to start relationship? Or does it make more
sense to end the incomplete task earlier and add a new task for the remainder
of the incomplete task and have that dependent on the higher priority task?
Thanks,
Michelle