T
terrapinie
This may be a weird question, or sound weird because I'm not quite
sure how to ask it... I have a project team of 10 people. We have 9
tasks of varying remaining length. We have allocated these resources
to the tasks so everyone has about 16 man-months of remaining work. I
need to estimate the remaining duration of these tasks with this
information. However, I cannot get project to do what I want. If I
put each person in with the % they will be working on each task, when
the task is complete, the % stays at, let's say, 15% until the work is
complete. This pushes the duration to be very large because these
people are working less than an hour for years. How can I make the
resources always working 8 hrs/day until the work for all tasks is
complete?
To help, here's the worksheet that my information is coming from:
Total Remaining
Man-Months|R1 |R2 |R3 |R4 |R5 |R6 |R7 |R8 |R9 |R10
Task1| 32 | | | 8 | 8 | 8 | 8 | | | |
Task2| 22 | | | | | | | 8 | 4 |10 |
Task3| 8 | | | | | | | 2 | 6 | |
Task4| 36 | | | 6 | 8 | 6 | | 6 | 6 | | 4
Task5| 12 | | | | | | 4 | | | | 8
Task6| 12 | | | | | 2 | 4 | | | 6 |
Task7| 8 | | 3 | 1 | 1 | | | | | | 3
Task8| 7 | | 7 | | | | | | | |
Task9| 22 |16 | 6 | | | | | | | |
_________________________________________________________
TOTAL| 159 |16 |16 |15 |17 |16 |16 |16 |16 |16 |15
This shows the total remaining man-months for the tasks, and the
man-months each person has had assigned to them.
I have calculated the percentage each task has allocated to it, as
well as the percentage each resource will be working, however, I
cannot figure out how to get accurate dates. I have even tried
putting one resource at 1000% and putting in the 200% or so that each
task has allocated. However, this just gives me the same finishing
date for each task. Any suggestions?
Thanks,
Laurie
sure how to ask it... I have a project team of 10 people. We have 9
tasks of varying remaining length. We have allocated these resources
to the tasks so everyone has about 16 man-months of remaining work. I
need to estimate the remaining duration of these tasks with this
information. However, I cannot get project to do what I want. If I
put each person in with the % they will be working on each task, when
the task is complete, the % stays at, let's say, 15% until the work is
complete. This pushes the duration to be very large because these
people are working less than an hour for years. How can I make the
resources always working 8 hrs/day until the work for all tasks is
complete?
To help, here's the worksheet that my information is coming from:
Total Remaining
Man-Months|R1 |R2 |R3 |R4 |R5 |R6 |R7 |R8 |R9 |R10
Task1| 32 | | | 8 | 8 | 8 | 8 | | | |
Task2| 22 | | | | | | | 8 | 4 |10 |
Task3| 8 | | | | | | | 2 | 6 | |
Task4| 36 | | | 6 | 8 | 6 | | 6 | 6 | | 4
Task5| 12 | | | | | | 4 | | | | 8
Task6| 12 | | | | | 2 | 4 | | | 6 |
Task7| 8 | | 3 | 1 | 1 | | | | | | 3
Task8| 7 | | 7 | | | | | | | |
Task9| 22 |16 | 6 | | | | | | | |
_________________________________________________________
TOTAL| 159 |16 |16 |15 |17 |16 |16 |16 |16 |16 |15
This shows the total remaining man-months for the tasks, and the
man-months each person has had assigned to them.
I have calculated the percentage each task has allocated to it, as
well as the percentage each resource will be working, however, I
cannot figure out how to get accurate dates. I have even tried
putting one resource at 1000% and putting in the 200% or so that each
task has allocated. However, this just gives me the same finishing
date for each task. Any suggestions?
Thanks,
Laurie