EV Analysts - TCPI Calculation with MS Project Pro 2003

M

Monika

I am looking at TCPI in several projects and the values do not look like they
are being calculated correctly.

TCPI = BAC (or baseline cost) - EV (or BCWP) divided by EAC - AC (or ACWP)

I don't know what it is doing but in some cases I am getting an odd value on
many lines - 4294967295. And, on other lines when I don't get that odd
value, the value is not what I come up with when calculating it manually
based on the formula above. When I try to get help on the TCPI field in MS
Project, it gives me a help screen for CPI....which is also an issue, I think.

Can anyone provide guidance? Has anyone heard of TCPI issues in 2003?
Thank you.
 