A
Annalisa
Hi all.
A questions:
Why does MS Project 2007 not consider cost-type resources in PV, EV, and AC
but consider them for BAC and EAC?
In this way, if I assign a cost-type resource to an activity I will never
have a % phisical completion =100% for my project! (In fact, the % of
Phisical completion for upper-level activities are based on EV-related
values).
Thx.
A questions:
Why does MS Project 2007 not consider cost-type resources in PV, EV, and AC
but consider them for BAC and EAC?
In this way, if I assign a cost-type resource to an activity I will never
have a % phisical completion =100% for my project! (In fact, the % of
Phisical completion for upper-level activities are based on EV-related
values).
Thx.