EV Calculation Problem

W

waldo

I was exploring doing EV with MS Project 2003 and found two problems that I
couldn't resolve. First, the task EAC cost was always equal to as BAC even
when there was either a positive or negative variance. The task EAC did not
match the calculated value using the formula in the MS information.

Also, the VAC was calculated correctly at the task level, but not at the
summary task level.

Any ideas why this would happen?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top