Can you help please. My problem is thus. We use MS 2002. Our tasks are
subcontracted and are entered as fixed cost over duration. Currently set to
fixed work and updated as % complete. Incomplete workis progressed. When
EV is applied some tasks have a variance between the total cost and the EAC
(we do not want the EAC to change as the cost to fixed). Is there anything I
can do to change the EAC to match the total costs or I am doing something
fundamentally wrong.