S
Strasser
EVA fields in MS Project standard are helpful in answering 3 important
questions:
1) On schedule? (as of status date)
2) On budget?
3) Estimate of the final cost of project, if same behavior continues
(EAC) (extrapolated cost)
I wish the estimated project completion date was displayed.
The variance value at the status date, added to the original
Project completion date, assumes that everything goes "as scheduled"
from the status date to the end of the project.
If accurate, I would like to extrapolate out (because things
might continue to be as "behind schedule as they have been up the to
status date.)
I have been using the following method.
I am worried that I may be way off.
My questionable method:
At status date:
Divide the original complete Project duration / SPI.
This gives an "extrapolated" complete project duration.
Then I create a "fake" task and add this "fake task" temporarily tothe
project.
Fake task starts at Project Act.Start.
Fake task uses the extrapolated duration value.
The "fake" task will use the project calendar to plot the extrapolated
project duration.
Then I use the Final date of the "fake" task as the extrapolated
project completion date.
Reactions?
Should I stick only to the project completion date that assumes the
rest of the project will proceed "on schedule" or is this
"extrapolated date" OK to use?
questions:
1) On schedule? (as of status date)
2) On budget?
3) Estimate of the final cost of project, if same behavior continues
(EAC) (extrapolated cost)
I wish the estimated project completion date was displayed.
The variance value at the status date, added to the original
Project completion date, assumes that everything goes "as scheduled"
from the status date to the end of the project.
If accurate, I would like to extrapolate out (because things
might continue to be as "behind schedule as they have been up the to
status date.)
I have been using the following method.
I am worried that I may be way off.
My questionable method:
At status date:
Divide the original complete Project duration / SPI.
This gives an "extrapolated" complete project duration.
Then I create a "fake" task and add this "fake task" temporarily tothe
project.
Fake task starts at Project Act.Start.
Fake task uses the extrapolated duration value.
The "fake" task will use the project calendar to plot the extrapolated
project duration.
Then I use the Final date of the "fake" task as the extrapolated
project completion date.
Reactions?
Should I stick only to the project completion date that assumes the
rest of the project will proceed "on schedule" or is this
"extrapolated date" OK to use?