Vadim Gerya, PMP
Hi All!
I have assigned cost resoure on task. Input cost for assignment. Saved
baseline. Input some actual (25%)
I tried to estimate BCWS and BCWP, but no values calculated fo cost
resource assigment (it timescale views) and no values added on task level.
Everything "ok" for work and material resources.
Project does not calculate EVM for cost resource assignments?