EVM and Cost Resource

  • Thread starter Vadim Gerya, PMP
  • Start date
V

Vadim Gerya, PMP

Hi All!

I have assigned cost resoure on task. Input cost for assignment. Saved
baseline. Input some actual (25%)

I tried to estimate BCWS and BCWP, but no values calculated fo cost
resource assigment (it timescale views) and no values added on task level.
Everything "ok" for work and material resources.

Project does not calculate EVM for cost resource assignments?
 
J

JulieS

Hello Vadim Gerya,

No, cost resources are not included in earned valued calculations.

If you try a google group search on this newsgroup for "cost
resources and earned value" you'll see quite a few discussions of
this topic.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project


in message
news:D[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top