R
RTucker
Hello all,
I have been challenged by external influences to make EVM function under the
following conditions:
Define the BCWS(hours)/Resource at CAP Level 5 (not at the lowest level
tasks) of the WBS/schedule, collect actual hours worked at the CAP, but
status the tasks (levels 6-12) using a 50/50 EV method.
Using MS Project, Actual Work becomes a calculated field when it is a
Summary Task. Therefore, if I report actual hours to teh Summary task using
the Task Usage table, then status a subordinate task's %Complete, MSP will
recalculate the Actual Work values entered.
It is my belief that the EVM logic built into the tool will not allow the
collection of CV data at L5 and SV data at Levels 6-12. Does anyone know of
a way to maintain the Actual Work hours and the 50/50 %Complete values so I
can extract the data into, perhaps, wInsight? I've experimented with
%WorkComplete versus %Complete. This brings more variables (effort versus
duration) into the fray.
I have the opportunity to use other tools if it helps this situation. All
textbook answers have been reviewed and tried. I am looking for someone's
unique tricks/experience to solve this one.
I have been challenged by external influences to make EVM function under the
following conditions:
Define the BCWS(hours)/Resource at CAP Level 5 (not at the lowest level
tasks) of the WBS/schedule, collect actual hours worked at the CAP, but
status the tasks (levels 6-12) using a 50/50 EV method.
Using MS Project, Actual Work becomes a calculated field when it is a
Summary Task. Therefore, if I report actual hours to teh Summary task using
the Task Usage table, then status a subordinate task's %Complete, MSP will
recalculate the Actual Work values entered.
It is my belief that the EVM logic built into the tool will not allow the
collection of CV data at L5 and SV data at Levels 6-12. Does anyone know of
a way to maintain the Actual Work hours and the 50/50 %Complete values so I
can extract the data into, perhaps, wInsight? I've experimented with
%WorkComplete versus %Complete. This brings more variables (effort versus
duration) into the fray.
I have the opportunity to use other tools if it helps this situation. All
textbook answers have been reviewed and tried. I am looking for someone's
unique tricks/experience to solve this one.