D
Diana
I am having trouble getting a formula to calculate fy to date and project to
date.
I need the cells to have a running total month to month. I have tried the
following:
Current Month Fy to Date Project to Date
=Sum(A1+B2) =Sum(B2+6248)
This formula will work for that row. But when I input different information
in the next row or use the enter key it adds that amount to cell B2. Any
explanations or help would be greatly appreciated as I have tried every thing
I know.
date.
I need the cells to have a running total month to month. I have tried the
following:
Current Month Fy to Date Project to Date
=Sum(A1+B2) =Sum(B2+6248)
This formula will work for that row. But when I input different information
in the next row or use the enter key it adds that amount to cell B2. Any
explanations or help would be greatly appreciated as I have tried every thing
I know.