Experts,
I have been importing excel data to Project for years and never seen this
problem. Today I was helping one of our users to import a list of assignments
from Excel to a project schedule. We opened the excel file and went through
the import wizard until we got to Finish. it went through but no data came
in. I tried the same excel and same project files on my computer and
everything worked fine. I did see that he did not have the "allow files with
legacy format to open", but when I checked it didnt help either. what ami
missing
Hadi
I have been importing excel data to Project for years and never seen this
problem. Today I was helping one of our users to import a list of assignments
from Excel to a project schedule. We opened the excel file and went through
the import wizard until we got to Finish. it went through but no data came
in. I tried the same excel and same project files on my computer and
everything worked fine. I did see that he did not have the "allow files with
legacy format to open", but when I checked it didnt help either. what ami
missing