The actual dates in my project file are linked from excel. Where the date
cell has not been filled out yet in excel, the actual date cell in project
displays NA.
All my calender settings are default and all tasks are multiples of full
days yet tasks with subtasks display durations that are incorrect and have
decimals. Could this be because of the "value" of NA? And is there a way
around it?
Once actual dates have been entered and there are no NA values for the
subtasks the task duration is correct and without decimals.