B
bxandi
Hi,
i´ve to change in huge project plan the names of all ressources. But
every time when i only exchange the names (working time an calender
are the same), the duration, begin, end and so on changes - what i
really dont need.
Is there any other possibility to exchange only the names an leace the
project plan as it is (search&exchange do work, but the timeplan is
afterwards not the same as before)
kind regards
bxandi
i´ve to change in huge project plan the names of all ressources. But
every time when i only exchange the names (working time an calender
are the same), the duration, begin, end and so on changes - what i
really dont need.
Is there any other possibility to exchange only the names an leace the
project plan as it is (search&exchange do work, but the timeplan is
afterwards not the same as before)
kind regards
bxandi