If you proceed with the negative lag approach you will be in deep trouble
in no time and your plan will be an unreadable, untrackable, tangled mess.
This is not a solution but just a good way to compound existing problems.
Don't say you weren't warned.
Are you sure that you even have a problem?
Sure, you can prevent any task in the plan from looking as though it is
occurring at the same time as the pour by making it a FS0 predecessor.
But you can achieve the same objective by making a task a FS0 successor to
the pour.
Either way, it's (slightly) bad modeling unless the pour really cannot
start until the predecessors are finished, or, as successors, the tasks
really cannot start until the pour has finished.
Why not just schedule everything as soon as possible, and let some tasks
appear to be happening at the same time as the pour, and add a bit to the
duration estimate for those tasks to allow for the anticipated (but not
certain) interruption that will occur if the task is in progress when the
pour starts?
Making all tasks either (directly or indirectly) FS predecessors or FS
successors of the pour, to force a space for the pour to occur with
nothing else going on, is a good approach, quite rigorous, easy to
coordinate etc. But it will make a lot of tasks and the pour critical (or
at least soak up the float on all of the paths), when they might not
really have to be on the critical path. It will make your project longer
than it might otherwise be. But it may well be reasonable to trade-off a
bit of extra duration in exchange for a bit more clockwork coordination.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au
__________ Information from ESET Smart Security, version of virus
signature database 4468 (20090929) __________
The message was checked by ESET Smart Security.
http://www.eset.com