M
Mac
Hi,
I am working through the Implementing and Administering Project Server 2007
by MS Project Experts, and I was looking for clarification on the Executive
Dashboard on page 594-595.
How do I calculate Percent Cost Overbudget, Percent Work Overbudget, Max
Cost and Max Duration? I only have a few projects in the Enterprise at this
time and very limited data to mess with and verify calculations. Also, what
type of graphical indicator limits are on each level?
I understand this may be defined by my business rules vs what the book says
but I am trying to understand what the book is showing.
Thanks.
I am working through the Implementing and Administering Project Server 2007
by MS Project Experts, and I was looking for clarification on the Executive
Dashboard on page 594-595.
How do I calculate Percent Cost Overbudget, Percent Work Overbudget, Max
Cost and Max Duration? I only have a few projects in the Enterprise at this
time and very limited data to mess with and verify calculations. Also, what
type of graphical indicator limits are on each level?
I understand this may be defined by my business rules vs what the book says
but I am trying to understand what the book is showing.
Thanks.