R
ricardo.marques01
We are trying to develop an executive report with EPM. This report not
only shows the current status of the projects but also the historical
information from the past like a progress bar that shows the "%
complete" for all projects against the time. This need is getting very
difficult to get because EPM report is very "today status oriented"!!!
We also tried to achieve this with cubes, but when the total work of
the project changes, also changes the "% complete" from previous
report periods, because they are calculated based on the total work of
the project.
So we worked on a workaround that saves the project status each time
the project manager saves the project into the database and with that
we can have historical information to fill our executive report.
Now, the question is: are we working with the right approach? Is there
a better solution? Are we missing something?
Regards,
Ricardo Marques
only shows the current status of the projects but also the historical
information from the past like a progress bar that shows the "%
complete" for all projects against the time. This need is getting very
difficult to get because EPM report is very "today status oriented"!!!
We also tried to achieve this with cubes, but when the total work of
the project changes, also changes the "% complete" from previous
report periods, because they are calculated based on the total work of
the project.
So we worked on a workaround that saves the project status each time
the project manager saves the project into the database and with that
we can have historical information to fill our executive report.
Now, the question is: are we working with the right approach? Is there
a better solution? Are we missing something?
Regards,
Ricardo Marques