D
deluth
I am currently using MSP2003. I would like to know if there's a way I can
see ALL the dependent tasks/resources for a specific milestone. Upon
double-clicking on the milestone, I can see all the predecessors for the
milestone, but I what I would like to see are all the resources that are
attached to those named tasks in the predecessor list. Is there a way to see
this? What I really want to get at is a way to quickly see how the milestone
is progressing at a high level. Also seeing which resource is at risk of
being on a critical path. Thanks in advance!
see ALL the dependent tasks/resources for a specific milestone. Upon
double-clicking on the milestone, I can see all the predecessors for the
milestone, but I what I would like to see are all the resources that are
attached to those named tasks in the predecessor list. Is there a way to see
this? What I really want to get at is a way to quickly see how the milestone
is progressing at a high level. Also seeing which resource is at risk of
being on a critical path. Thanks in advance!