pls Explain how do I link one task to the middle of another task?
R Rod Gill Sep 14, 2007 #2 Hi, Add a lag of 50% to a start-Start or -50% to a Finish-Start -- Rod Gill Project MVP Project VBA Book, for details visit: http://www.projectvbabook.com NEW!! Web based VBA training course delivered by me. For details visit: http://projectservertraining.com/learning/index.aspx