I have couple questions, does anyone know how to:
1) Export data from MS Project to Excel (Task Table) which does NOT include
100% complete tasks?
2) I also would like to EXCLUDE exporting of summary tasks - what I do as a
temp work-a-round is after exporting data, in Excel sort the tasks by
Resource Name which pushes all the summary tasks toward the end as they don't
have resource assigned - but I AM THINKING THERE MIGHT BE A BETTER AUTOMATED
WAY than what I am doing..
Thanks for your help!
Lilly
I have couple questions, does anyone know how to:
1) Export data from MS Project to Excel (Task Table) which does NOT include
100% complete tasks?
2) I also would like to EXCLUDE exporting of summary tasks - what I do as a
temp work-a-round is after exporting data, in Excel sort the tasks by
Resource Name which pushes all the summary tasks toward the end as they don't
have resource assigned - but I AM THINKING THERE MIGHT BE A BETTER AUTOMATED
WAY than what I am doing..
Thanks for your help!
Lilly