M
Matt Collins
I am using MS Project 2003
I am trying to chart resource usage info in excel but using resource groups.
Example: I have 40+ resources in three groups, Design, Production,
Instalation. I want to chart all three group totals by day/week/month on the
same chart.
Currently I copy and paste the day by day resource usage info for a 6month
period into excel. Then I remove the work units (hrs) using find and replace.
Then I sum up the totals for each resource group and finaly hide the
individual resource rows before charting.
Surely there is an easier way to achieve this?
Could I do this if I upgrade to Project Server etc.
Can anybody help or sugest other ways of achieving this outcome. Many thanks
in advance
Kind regards
Matt Collins
I am trying to chart resource usage info in excel but using resource groups.
Example: I have 40+ resources in three groups, Design, Production,
Instalation. I want to chart all three group totals by day/week/month on the
same chart.
Currently I copy and paste the day by day resource usage info for a 6month
period into excel. Then I remove the work units (hrs) using find and replace.
Then I sum up the totals for each resource group and finaly hide the
individual resource rows before charting.
Surely there is an easier way to achieve this?
Could I do this if I upgrade to Project Server etc.
Can anybody help or sugest other ways of achieving this outcome. Many thanks
in advance
Kind regards
Matt Collins