D
davegb
I am trying to recreate a report I saw in Excel, imported from
Project. It displayed a page for each resource in the resource pool.
In the upper left cell was the resource's name, then the column
headers. Below that was an "overallocated hours" row, filterable with
Autofilter. Below that were remaining availble hours, and total work
hours. below that was the list of tasks the resource is assigned to.
Across the top are Work, Actual Work, Start, Finish, the a column for
each week over a specified time period. The work on each task for the
week was displayed in each column.
Does anyone know how to create this type of report? Any help would be
greatly appreciated.
Dave Bellamy
Project. It displayed a page for each resource in the resource pool.
In the upper left cell was the resource's name, then the column
headers. Below that was an "overallocated hours" row, filterable with
Autofilter. Below that were remaining availble hours, and total work
hours. below that was the list of tasks the resource is assigned to.
Across the top are Work, Actual Work, Start, Finish, the a column for
each week over a specified time period. The work on each task for the
week was displayed in each column.
Does anyone know how to create this type of report? Any help would be
greatly appreciated.
Dave Bellamy