J
Jim Aksel
Project produces two items of interest (1) Task Usage view delineating time
phased hours/dollars/BWCS, etc and resources for each Task. (2) A Work
Report showing the same items (Report: Work Load/Task Usage).
When I attempt to export this data to Excel using the Export features in MS
Project 2002, the resulting spreadsheet automatically totals the items for
all resources and rolls them up to the task level. I do not want the
roll-up.
What I would like to see (in Excel) is a task list with each individual
resource spread underneath it with time phased data .... exactly how it shows
in project. How?
phased hours/dollars/BWCS, etc and resources for each Task. (2) A Work
Report showing the same items (Report: Work Load/Task Usage).
When I attempt to export this data to Excel using the Export features in MS
Project 2002, the resulting spreadsheet automatically totals the items for
all resources and rolls them up to the task level. I do not want the
roll-up.
What I would like to see (in Excel) is a task list with each individual
resource spread underneath it with time phased data .... exactly how it shows
in project. How?