T
Terry Mc
Not real well versed in VBA, but I need to be able to export data out
of project in the following format (note: resources have names but #'s
are there for demo purposes):
WBS Week Resource Work
1.1.1 9/4/2006 1 25
1.1.1 9/4/2006 2 25
1.1.1 9/4/2006 3 30
1.1.1 9/4/2006 4 40
1.1.1 9/4/2006 5 15
1.1.1 9/11/2006 1 20
1.1.1 9/11/2006 2 40
1.1.1 9/11/2006 3 40
1.1.1 9/11/2006 4 35
1.1.1 9/11/2006 5 30
1.1.1 9/18/2006 1 24
1.1.1 9/18/2006 2 18
1.1.1 9/18/2006 3 9
1.1.1 9/18/2006 4 1
1.1.1 9/18/2006 5 6
etc etc etc etc
I have an existing Access database that will use the planned work
schedules from project to compare to our actual hrs enterered into our
online timekeeping system. At this point, if I can get the info out of
Project and into Excel in this format, I can do the types of analysis
that I need done. I realize that I could do more to make this easier,
but any help at just getting this information out would be greatly
appreciated.
of project in the following format (note: resources have names but #'s
are there for demo purposes):
WBS Week Resource Work
1.1.1 9/4/2006 1 25
1.1.1 9/4/2006 2 25
1.1.1 9/4/2006 3 30
1.1.1 9/4/2006 4 40
1.1.1 9/4/2006 5 15
1.1.1 9/11/2006 1 20
1.1.1 9/11/2006 2 40
1.1.1 9/11/2006 3 40
1.1.1 9/11/2006 4 35
1.1.1 9/11/2006 5 30
1.1.1 9/18/2006 1 24
1.1.1 9/18/2006 2 18
1.1.1 9/18/2006 3 9
1.1.1 9/18/2006 4 1
1.1.1 9/18/2006 5 6
etc etc etc etc
I have an existing Access database that will use the planned work
schedules from project to compare to our actual hrs enterered into our
online timekeeping system. At this point, if I can get the info out of
Project and into Excel in this format, I can do the types of analysis
that I need done. I realize that I could do more to make this easier,
but any help at just getting this information out would be greatly
appreciated.