Export to Excel 2007

N

Neal

Hi,
I would like to export my tasks from MS Project 2007 into an Excel 2007
spreadsheet and maintain the outline. When I do this all indents are lost and
all tasks are left justified.
Is there a way to export and have the indents preserved?
Thanks, Neal...
 
J

JulieS

Hi Neal,

If you export the Outline Level field along with your task
information you can use Autofilters and quickly format the outline
and bolding in Excel. Other than developing some VBA code which
formats the data in Excel once exported, that is probably the
fastest answer.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
T

Trivikram

Hi... Neal,

There is a 2 or 3 step process for accomplishing this task. You should use a
macro to export the tasks to excel in hirarchy and then copy & paste other
fields such as duration, start, finish, etc (as required). The process is as
follows,

1. http://masamiki.com/project/macros.htm - Find the macro & procedure to
create it in your MSP.

2. http://masamiki.com/project/export-hierarchy-to-excel.html - Download &
use this macro to export the task in hirarchy.

3. Copy & paste the other required fields.

Hope this helps!!!

Trivikram.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top