K
kees van loon
I'm working on with a consolidated projectfile and export the "resource
usage" screen to excel. I created a extra colum "project" to see the project
the resource has to work on.
I have two problems:
1: The colum work shows as hours, and i prefer to have it in days, is that
possible ?
2: The left and right part I copy and past to Excel. In excel the time is
writen as "6H" and I can't calculate on the cell because it is a text field.
is there a solution for ?
I also had tried to export to excel with "save as" but then it is not
possible to save the "project" field, only the task a resource is working is
exported on but not the project. (the subproject name) or is there still
another way ?
usage" screen to excel. I created a extra colum "project" to see the project
the resource has to work on.
I have two problems:
1: The colum work shows as hours, and i prefer to have it in days, is that
possible ?
2: The left and right part I copy and past to Excel. In excel the time is
writen as "6H" and I can't calculate on the cell because it is a text field.
is there a solution for ?
I also had tried to export to excel with "save as" but then it is not
possible to save the "project" field, only the task a resource is working is
exported on but not the project. (the subproject name) or is there still
another way ?