Hey,
I have our Project Server listed in the "Trusted Sites" in IE. Also, I
have every ActiveX control selection set to "Enable" for the Custom
Level security settings. Even with these settings, I still receive
the following error messages when click on Export Grid to Excel from
the Project Center in PWA:
An error occurred while exporting the grid data to Excel.
Because of this error, you can only copy the XML data to the Clipboard.
Do you want to continue?
When I receive this message, Excel opens and populates the spreadsheet
with project data.
I can certainly live with saving the file as .xls and moving on, but
our CIO is using the Export Grid to Excel link. How do I resolve this
so the export is seamless?
HELP!?!
RDA