Export to Excel

H

Harry

I want to export the resource usuage view across 12 weeklt periods showing
actual work effort from a project file in project Server to an Excel file .
How can I do this?

Harry
 
D

Dale Howard [MVP]

Harry --

The only way to export the Resource Usage view to Excel is to create a
custom macro in VBA. Otherwise, the best you can probably do is to use the
Analyze Timescaled Data Wizard. Hope this helps.
 