T
TerryHolland
I am new to MS Project. I have set up a project that has a number or
summary tasks each with a set of sub-tasks. Some of the sub-tasks also
have sub tasks.
What I want to be able to do is export tasks to Excel creating a sheet
that enables me to easily sum the number of 'work units' involved in
the project ie
Main 1 5 days
Sub 1 1 day
Sub 2 4 days
Sub 2 Sub 1 1 day
Sub 2 Sub 2 3 days
In Project it is obvious that the duration for Main 1 is the sum of the
times for Sub 1 & Sub 2 (which in turn is the sum of Sub 2 Sub 1 & Sub
2 Sub 2).
However, when this gets exported to Excel I get the following
WBS Name Duration
1 Main 1 5 days
1.1 Sub 1 1 day
1.2 Sub 2 4 days
1.2.1 Sub 2 Sub 1 1 day
1.2.2 Sub 2 Sub 2 3 days
This format makes it 'impossible' to derive the total amount of work
for project, Is there any way to isolate the figures that are actually
for work and not for summaries while still keeping the summaries in the
sheet for clarity?
summary tasks each with a set of sub-tasks. Some of the sub-tasks also
have sub tasks.
What I want to be able to do is export tasks to Excel creating a sheet
that enables me to easily sum the number of 'work units' involved in
the project ie
Main 1 5 days
Sub 1 1 day
Sub 2 4 days
Sub 2 Sub 1 1 day
Sub 2 Sub 2 3 days
In Project it is obvious that the duration for Main 1 is the sum of the
times for Sub 1 & Sub 2 (which in turn is the sum of Sub 2 Sub 1 & Sub
2 Sub 2).
However, when this gets exported to Excel I get the following
WBS Name Duration
1 Main 1 5 days
1.1 Sub 1 1 day
1.2 Sub 2 4 days
1.2.1 Sub 2 Sub 1 1 day
1.2.2 Sub 2 Sub 2 3 days
This format makes it 'impossible' to derive the total amount of work
for project, Is there any way to isolate the figures that are actually
for work and not for summaries while still keeping the summaries in the
sheet for clarity?