Export to Visio timeline

S

Suze

Anybody know how to get certain dates from a Project file into Visio so it
will automatically make a timeline?

If not, is there some other tools that'll read the dates to make a timeline?
I'd need to be able to tell the program that only certain dates are
milestones.
 
S

Simon

Will it not work to set milestones in project and then roll these up? Not sure why you need it in Visio. [Just in case, a 0 day task in project = a milestone]
 
S

Steve House

Visio can open and import data directly from the mpp file to make a
timeline. If the dates of interests are milestones in the project file,
Visio will record them as milelstones also.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top