Exporting non-working day between projects

M

Mario - Roma

I have a large project with many resources and lots of resource-specific non
worlking days.
Can I export the list of non-working days from one project to another one?
A macro to read non working days and to export them would be excellent...
Regards
Marius
 
J

JulieS

Hello Marius,

If you copy and paste the resource record (row) between project files you
will also copy the resource's calendar.

If you have several resources with similiar working definition, consider
creating a new base calendar and setting that for the resources. You may
copy base calendars from project file to project file through the Tools >
Organizer command.

I hope this helps.

Julie
 
M

Mario - Roma

Excellent hint!
It works fine, as it let me perform my updates in a secondary file and copy
them to my master file when I am sure they are ok.
Thank you
Mario
 