I have set up some reporting in Access 2000 and the info is fed from
Project 2000. For some reason, SOMETIMES, all the fields aren't
populated for every record. What I mean to say is that most of the
time, when I do the export and open the table in Access, the Task Name
field is blank after about 50 or so records. The affects a few other
fields as well.

I've found that if I do an export to an Excel workbook and THEN try
exporting to Access again, it works fine. Not a terrible workaround,
but slightly cumbersome.

Any ideas?
 