Exporting/reading percentage completion data

D

DM

Hello,

does anyone know which tables I'd look at to see the costs to date on a
project assuming I update it using percentage completion? i.e. I have a
$100k project and am 61% complete - somewhere there should be the data that
shows $61k of costs have been incurred - anyone know which table this
information is in? I assume this table would show information for the
summary task, and sub-tasks?

Thanks

DM
 
D

DM

Is this for Project 2003 or 2007? We're using 2007 and I cant see a tabled
called 'cost'??

Thanks
 
D

DM

Ah - sorry, I meant within the SQL tables - I want to have access to the
data to export into Excel or be made available to another SQL database such
as a finance package.

Thanks

DM
 