Hi,
I'm using project server 2007, and wanted to export timehseets of the
selected resources along with their tasks list mentioned in their time
sheets in an excel sheet.
I only see one option where it exports the aggregated number of hours only
of all the selected resources. Is there any way i can do as mentioned above?
The other problem that i have is about approving time sheets. With myself as
the administrator and project managers as time sheet manager for their
resources, when a resource submits a time sheet, it first goes to the PM as
one would expect. But when the PM tries to approve it, the workflow asks it
to send for further approval. While what i am looking for is that once a PM
approves it, it shouldnt ask for any further approvals. I guess i missed
some rights for the PM. Any idea what i missed?
Best regards,
Farooq Khan
I'm using project server 2007, and wanted to export timehseets of the
selected resources along with their tasks list mentioned in their time
sheets in an excel sheet.
I only see one option where it exports the aggregated number of hours only
of all the selected resources. Is there any way i can do as mentioned above?
The other problem that i have is about approving time sheets. With myself as
the administrator and project managers as time sheet manager for their
resources, when a resource submits a time sheet, it first goes to the PM as
one would expect. But when the PM tries to approve it, the workflow asks it
to send for further approval. While what i am looking for is that once a PM
approves it, it shouldnt ask for any further approvals. I guess i missed
some rights for the PM. Any idea what i missed?
Best regards,
Farooq Khan