We have implemented Project 2003 in our organization. I have couple of
queries on OLAP cube:
1. We would want to extend the OLAP cube to the tasks level, in the sense we
would want to know the baseline start and actual start for each task so that
we would know the variances for each task. How can i extend the OLAP cube to
get the information?
2. Also i would want the tool to send a mail on a daily basis on the list of
tasks to be performed each day and also the remaining work pending for the
previous tasks for each resource. How can i configure the same
We have implemented Project 2003 in our organization. I have couple of
queries on OLAP cube:
1. We would want to extend the OLAP cube to the tasks level, in the sense we
would want to know the baseline start and actual start for each task so that
we would know the variances for each task. How can i extend the OLAP cube to
get the information?
2. Also i would want the tool to send a mail on a daily basis on the list of
tasks to be performed each day and also the remaining work pending for the
previous tasks for each resource. How can i configure the same