C
Chris
Hello,
two PMs wanted to use external dependencies to connect their schedules but
they didn't have permission to do it (each PM was only allowed to modify his
own schedule).
I temporarily gave one of the PMs additional permissions and he was able to
create the external dependency. I then switched back to the initial settings.
Now the PM who created the external dependency is still able to modify both
schedules, while the other PM can only edit his own schedule. Is this normal?
How can I get back to my original configuration: each PM can only modify his
own schedule?
Thanks,
Chris
two PMs wanted to use external dependencies to connect their schedules but
they didn't have permission to do it (each PM was only allowed to modify his
own schedule).
I temporarily gave one of the PMs additional permissions and he was able to
create the external dependency. I then switched back to the initial settings.
Now the PM who created the external dependency is still able to modify both
schedules, while the other PM can only edit his own schedule. Is this normal?
How can I get back to my original configuration: each PM can only modify his
own schedule?
Thanks,
Chris