Andy S
I have two projects linked together with external dependencies. After
a few weeks, we removed some of the dependencies that linked the tasks
from both projects together. In both project files in Project Pro
2003, these dependencies are shown as removed. However, in PWA 2003
Project Center, the external dependencies still show up. We have done
every publishing option multiple times on both schedules, yet the
tasks that used to be linked still show up in PWA Project Center.
Is there something I missing?